AI drives data center construction in Germany to record levels
Germany remains Europe’s largest data center hub and is investing more than ever before. However, the new Bitkom study also shows how quickly the gap with the U.S. and China is widening—and where the opportunity lies for the industry.
16 Nov 2026Share
Never before has so much money been invested in data centers in Germany: Operators will invest 23.5 billion euros in 2026, 57 percent more than in the previous year. These findings come from the study “Data Centers in Germany 2026,” which was conducted by the Borderstep Institute on behalf of the digital industry association Bitkom and presented by the association on November 3 in Berlin. Approximately 18 billion euros will go toward IT hardware such as servers and storage, and 5.5 billion euros toward buildings and building systems. In 2024, the total investment volume had stood at 12.9 billion euros.
The study estimates the IT connected load of German data centers at 3,300 megawatts for 2026; in 2015, it was 1,660 megawatts. By 2035, capacity is expected to nearly triple to around 9,700 megawatts. Just over 2,000 data centers in the country have a connected load of more than 100 kilowatts. The approximately 100 large facilities exceeding five megawatts now account for 52 percent of the total capacity.
AI Is Moving from the Exception to the Norm
The driving force is artificial intelligence. By 2026, 670 megawatts—or 20 percent of capacity—will be accounted for by AI and high-performance computing. By 2035, this figure is expected to reach around 5,300 megawatts, more than half of the installed capacity at that time. For planners and equipment suppliers, this means a new generation of facilities with higher power densities, new cooling concepts, and more robust grid connections.
It is revealing to see what profile the industry attributes to the region. In the accompanying survey of operators and experts, 68 percent expect that primarily smaller AI models will be trained in Germany. 54 percent view research institutions as key drivers of AI development, and 46 percent anticipate a special role for industrial AI—that is, AI in machines, systems, and industrial processes. Respondents thus describe the interface where computing power meets industrial process knowledge.
Hesse Leads, Brandenburg Catches Up
Regionally, Hesse remains the largest location with approximately 1,200 megawatts of IT connection capacity. According to the association’s assessment, the high density there has given rise to a distinct ecosystem of companies, network operators, and cloud and IT service providers. Brandenburg is considered the rising star: while approximately 104 megawatts are currently in operation, 1,301 megawatts are under construction.
The global benchmark is shifting
In a European comparison, Germany leads with 3.3 gigawatts, ahead of the United Kingdom (2.9), France (2.0), and Ireland (1.7). The global benchmark is different. The U.S. will already have around 47 gigawatts by 2025. The study projects 160 gigawatts there by 2035, 90 in China, and 37 across all of Europe. “The AI competition is also a competition for computing power,” said Bitkom President Dr. Ralf Wintergerst.
Even the national goal is no sure thing. The federal government aims to double capacity by 2030, which would correspond to about 6,000 megawatts; the trend indicated by the study points to 5,500 megawatts. Two-thirds of those surveyed view the federal government’s data center strategy positively, but only 20 percent expect it to be implemented quickly.
Electricity, Grid, and Permits Are Key
The bottleneck lies less in capital than in infrastructure. Data centers and smaller IT installations will require approximately 23 billion kilowatt-hours of electricity by 2026. The study projects 35 to 38 billion kilowatt-hours for 2030 and 56 to 70 billion kilowatt-hours for 2035. Bitkom is therefore calling for competitive electricity prices, faster grid expansion, more efficient allocation of existing connection capacity, designated land areas, and simpler, digital permitting procedures.
Up to Three Times More Energy-Efficient
At the same time, the study documents progress in efficiency. The PUE value—which measures a data center’s total energy consumption relative to its IT consumption—has fallen from 1.63 to 1.42 since 2020. Modern servers are up to three times as energy-efficient as systems from 2021. Regarding waste heat, the association calls for better integration into municipal heat planning and stronger economic incentives for consumers.
Surge in Orders for Equipment Suppliers
For the industry, these findings are doubly relevant. It is a customer of this infrastructure when it incorporates AI into development and production. And it is a supplier, since transformers, switchgear, cooling technology, and automation systems come from its factories. The fact that 5.5 billion euros will be invested in buildings and technology in 2026 alone—nearly twice as much as in the previous year—also represents a surge in orders for these equipment suppliers.
Related Exhibitors
Interested in news about exhibitors, top offers and trends in the industry?
Browser Notice
Your web browser is outdated. Update your browser for more security, speed and optimal presentation of this page.
Update Browser